Patios laid on a proper base

Natural stone, porcelain or concrete flags, bedded on full mortar over a compacted MOT Type 1 base, with falls that take water away from the house. The bit you can't see is why it lasts.

Placeholder image: a laid patio

What's included

  • Setting out, levels and falls, with the finished surface at least 150 mm below the damp-proof course
  • Excavation and muck-away
  • 100–150 mm of MOT Type 1 sub-base, compacted in layers
  • Slabs bedded on a full sand and cement mortar bed, never dot-and-dab
  • Slurry primer on the back of porcelain and sandstone so it bonds
  • Joints pointed with a brush-in compound or a sand and cement mix
  • Edging, steps and channel drains where the levels need them
  • Cleaned down at the end, and sealed if you want it
Placeholder image: hard landscaping detail

The process

How it goes

  1. Quote visit. Rory measures up, checks levels and drainage, and brings slab samples if you're unsure.
  2. Written quote. Every stage itemised, including the waste.
  3. Dig out. Excavated to depth, with the spoil taken away.
  4. Base. MOT Type 1 laid and compacted with a plate compactor.
  5. Lay. Slabs bedded on mortar, checked for level and fall as we go.
  6. Point. Joints filled and the surface cleaned.
  7. Handover. We'll tell you when it's ready for furniture and how to look after it.

Typical timescales

Typical 20 m² patio
3–5 days
Large patio with steps or low walls
1–2 weeks
Before heavy furniture goes on, while the mortar cures
48 hours

Materials

Materials we use

  • MOT Type 1 crushed stone sub-base, compacted in layers with a plate compactor.
  • 4:1 sharp sand and cement mortar bed under every slab.
  • Indian sandstone. Riven, natural, and every slab slightly different.
  • 20 mm outdoor porcelain. Hard-wearing, low-maintenance, laid with a slurry primer.
  • Concrete flags from Marshalls or Bradstone for a cost-effective finish.
  • Brush-in jointing compound such as Azpects EASYJoint, or a traditional sand and cement point.

Questions people ask

  • Porcelain or Indian sandstone?

    Porcelain is very hard, resists stains and stays consistent in colour. Sandstone is natural, a little softer, and mellows with age. Porcelain costs more to lay because it needs a slurry primer and diamond cutting.

  • Why not just lay the slabs on sand?

    Slabs on dry sand rock, sink and let weeds through. A full mortar bed on a compacted MOT Type 1 base is how you stop that.

  • Will I need drainage?

    Every patio needs a gentle fall away from the house so rain runs off. If the water has nowhere to go, we add a channel drain or a soakaway, and it's shown on the quote.

  • Can the patio be level with my back door?

    It has to sit at least 150 mm below the damp-proof course, roughly two bricks. If that leaves a step down from the door, we'll design a proper step in.

  • How soon can I use it?

    You can usually walk on it after 24 hours. Give it 48 hours before heavy furniture or a barbecue.

  • Does a patio need sealing?

    Not always. Porcelain doesn't need it. Sealing sandstone helps with stains but slightly changes the look, so we'll show you a sample first.

Ready for a patio that stays put?

Book a free visit. Rory will measure up, check the levels and send you an itemised quote.

Book a free quote visit